Project: Fourchon Pump Station
Equilon Pipeline, L.L.C.
Installation of underground/aboveground electrical and instrumentation for a new four (4) 7000HP, 13.8KV pump station in Fourchon, Louisiana.
Customer: |
|
Owner: |
Equilon |
Type: |
Cost-plus approximately $1,300,000 |
Duration: |
Approximately 5 months |
MEITEC was responsible for installation of the new 13.8
KV switchgear in
LOOP,
LLC’s Powerhouse, a new 13.8
KV switch house (with variable frequency drives,
capacitance and across the line capabilities), a new (
REE) Remote Electric
Enclosure complete with
PLC control and 480
VACMCC’s, all lighting, conduit,
cable tray,
CLX cable, control panels, etc.
This project began with engineering 80% complete, requiring MEITEC
project management and supervision to field engineer all of the installation
techniques and criteria.
MEITEC coordinated all civil and mechanical/structural disciplines associated with
this project to relieve the site civil/mechanical contractor of any additional responsibilities.
This very fast track job was completed ten (10) days before required completion/
start-up.
Our peak manpower level was 62 craftsmen, working an average of seven (7) days
per week, ten to twelve (10-12) hours per day. Due to the fast track nature of the
project, twenty-five (25) craftsmen were on site the first week.
Contact us for more information.