Project:  Waller Power Barges

Project Images



Waller Marine Margarita I and Josefa Rufina I Power Barge Project


These power barges will become the world's largest floating power generation facility when installed side-by-side.
The two power barges were built at Signal International's shipyard in Orange, Texas.
The generation facility is comprised of two floating power plants and each is installed with a single GE 7FA gas turbine generator, each having an output of 171 MW (ISO).
  • Inspect all cables and cable tray.
  • Ensure proper size cable dependant upon the load.
  • Ensure proper grounding.
  • Record all cable certification, to include in the turn-over folders, and to submit to ABS.
  • Verify scope drawings, and red-line as needed.
  • Verify all terminations, and perform point to point tests prior to energizing circuit.
  • Ensure all cables are tested (megaohm), and results are reported.
  • Schedule and record the results of third-party primary and secondary testing of the high amperage circuit breakers.
  • Verify discrepancies have been cleared throughout the course of the job.
  • Pre-commission systems and Report.
  • Build turn-over folders, to include scope drawings, equipment located in system, all test results (megohm, point to point, primary and secondary injection, FAT, etc...), all pre-commission checklists, and punch-list.